High WIP is not a sign that operators are not trying. It is a sign that the line is broken. When one operation finishes, the material is moved away, waits, is found again, and only then goes to the next operation. One-piece flow removes that waiting, moving and searching so material flows piece by piece.
The problem
- Output was stuck. The target was 350 → 400 a day, and overtime could no longer make up the difference.
- WIP piled up between operations. 2,874 pieces on the line, much of it "finished, waiting for the next operation", occupying space and cash and hiding problems.
- Time went into waiting and changing over. 28.5% of operator time spent waiting, 10.67 hours of downtime, 5 hours of changeover — the time actually spent working was fragmented.
- No space. Semi-finished goods took more than half the floor; there was nowhere to add a line or equipment.
- Nobody owned the bottleneck. The line was held back by one or two slow stations; other stations running faster made no difference, yet everyone worked to their own rhythm.
The seven steps
- 1 · Training. Make sure the team understands what is being done and why; otherwise the first action reverts.
- 2 · Define the task. Which line, to what level, and who owns it.
- 3 · Analysis. Work-element analysis and line balancing: break every station's motions down to seconds and work out who is busy, who is idle and where the blockage is.
- 4 · Solution. Re-sequence stations, balance the load, design workstations, set PFEP (where each part is stored, in what quantity, and how it is replenished).
- 5 · Improvement. Change the layout, build fixtures, change material handling — put the solution on the floor.
- 6 · Check. Watch results on an hourly output board and find the cause on the spot when output drops.
- 7 · Sustain. Turn the new way of working into standard work and hold it.
The tools we used
- Before/after layout: from "workshops by process" to "lines by product family".
- Work-element analysis and line balancing: find the bottleneck station and level the load.
- Workstation design: redesign height, bin position and tool placement around ergonomics and takt.
- PFEP: usage, packaging, storage point and replenishment frequency for every part, fixed on one sheet.
- Hourly output board: the floor can see how much was made this hour and how far short it is.
- Bottleneck fixture: a dedicated fixture for the slowest operation to cut its time.
Results
Bars are illustrative, drawn to the before/after ratio; figures come from the project's before/after records.
Why WIP could fall so far
WIP was not managed down; it was flowed down. Stations connected, material at the station, takt aligned — when one operation finishes the next picks up immediately, and nothing needs to pile up. Those 2,700-odd pieces were paying for the break and the wait.
This is also how to judge whether a line can run one-piece flow: look at where WIP piles. Between two operations means the line is broken; in front of one station means that station is the bottleneck.
Who this is for
- High-mix, low-volume assembly plants with lines split by process and high WIP.
- Plants that want more output but have reached the limit of overtime.
- Plants short of space for a new line, where semi-finished goods are quietly taking up the floor.
- Bottlenecks covered by effort and overtime, with no dedicated fixtures or workstation design.
- Not for: very large single pieces (heavy equipment), or products so unstable that the routing changes every day.
Answer one question first: where does your WIP pile up?
A two-day on-site diagnostic: walk the line, see where semi-finished goods pile up, work out where the bottleneck is and who is using the space, and leave a 90-day one-piece-flow roadmap. No system first, no large programme first.
Austin Zhai | Plan · Kit · Deliver zhaiweidong.com austin.zhai@hotmail.com